August 01, 2008

Fit Gap on Schedule

(Project Report Aug. 2008) Nearly 50% of the Fit-Gap analysis is complete and the project team is on schedule to complete conference room pilots and infrastructure testing by the first week of September. The number of gaps identified so far are more than expected, but none are "show stoppers" at this stage. August Project Progress Report Capital Committee meeting logistics are also underway.